Route and site
Site address, postcode and the route or working area marked on a drawing.
Utility and civils routes cross farmland, verges, tree roots, wet ground and protected sites. The temporary access has to fit commitments already made for soils, trees, water and wildlife. This guide sets out what UK guidance says, what to check before mobilising, and where matting fits and where it does not.
TM200 MegaDeck HD+. Supplier application image.
Matting keeps plant off the soil and lifts out when the works finish, but it does not replace a permit, a tree protection design or a watercourse crossing. Start from the scheme's environmental commitments, map the constraints, match the protection to the load, keep plant on the route and record the ground at installation and uplift. In England, work near main rivers and on SSSIs can need permission before it starts.
Cable routes, pipelines and overhead line works often cross land the scheme has promised to look after: farmland that goes back into production, tree roots beside the route, ditches and rivers, and sometimes protected sites.
The temporary access has to fit inside those promises. Matting spreads plant loads across the surface, keeps tyres and tracks off the soil and lifts out when the works finish. It is one tool in the plan, not the plan itself, and the class and layout still have to suit the ground and the loads.
No single UK standard covers temporary access matting on sensitive ground. The guidance below comes from soil, tree, water, protected site and invasive plant sources. Each is quoted with the scope it was written for, so you can judge how far it applies to your route.
| Point | What the source says | Source and scope |
|---|---|---|
| Keep traffic to set routes | Confine movement of trucks or dumpers to designated temporary haul routes. | Defra soils code of practice (2009)Written for soil handling on construction sites |
| Do not strip or move wet soil | The code advises against stripping or handling soil during or after heavy rainfall, or when there are pools of water on the surface. It is soil handling guidance, not a ban on all site work in wet weather. | Defra soils code of practice (2009)Written for soil stripping and handling |
| Decompact before reinstating | Decompact subsoil before placing topsoil, to break up panning, reduce flood risk and promote deeper root growth. | Defra soils code of practice (2009)Written for soil reinstatement |
| Protect roots by load | For light plant up to 2 tonnes: proprietary interlinked ground protection boards on a compression-resistant layer over a geotextile. Heavier vehicles: an engineered system designed with arboricultural advice. | BS 5837:2012 clause 6.2.3.3, as quoted in a published arboricultural method statementTrees in relation to construction |
| Utility works near trees | Three zones around each tree: Prohibited (1 metre from the trunk), Precautionary (4 times the tree circumference) and Permitted. In the Precautionary Zone, prevent all vehicle movement, plant use or material storage, or install suitable ground protection before any activity. | Street Works UK Volume 4, Issue 3 (2026), formerly NJUG Volume 4Utility apparatus near trees |
| SSSIs and statutory undertakers | Statutory undertakers such as water and electricity companies must request assent from Natural England for activities likely to damage an SSSI. Natural England usually replies within 28 days to give or decline assent, and no written reply within 28 days should be taken as assent declined. | GOV.UK, Natural England guidancePublic bodies in England |
| Work near main rivers | A flood risk activity permit can be needed within 8 metres of a main river bank, or of a flood defence or culvert on a main river (16 metres for both if the river is tidal), and within 16 metres of a sea defence. Ordinary watercourses go to the council or internal drainage board. | GOV.UK, Environment Agency guidanceEngland only |
| Invasive plants | Establish designated haulage routes, prevent plant movement through invasive plant areas, and use Check, Clean, Dry with wash-down stations where needed. | CECA handbook for site managers (June 2026)Civils sites |
| Plant crossing buried services | Where heavy plant may have to cross a vulnerable service, provide defined crossing points, keep them to a minimum, mark them clearly and allow no crossing elsewhere. Where an existing road does not protect the service, reinforce the crossing with sleepers, steel plates or a reinforced concrete raft as necessary. The owner or operator of the service advises on the reinforcement. | HSE, HSG47 (third edition, 2014), paragraph 69All underground services |
| High pressure gas pipelines | Construction traffic crosses only at previously agreed locations, fenced on both sides. The pipeline is protected at the crossing by temporary rafts of sleeper or reinforced concrete construction at ground level, and the network decides the raft from ground conditions, vehicle types and crossing frequency. | Wales & West Utilities, T/SP/SSW/22 (April 2026)Gas pipelines above 2 bar |
| Japanese knotweed | You can be prosecuted for causing knotweed to spread into the wild. Brush down or jet-wash vehicles and check for trapped plant or rhizome. | GOV.UK, Environment Agency guidanceEngland |

A stone haul road usually means stripping topsoil, laying a membrane, importing aggregate, then digging it all out again and reinstating the land. On a long programme with very heavy, constant traffic that can still be the right answer.
A matted route sits on the surface. Panels are placed, connected, inspected and lifted, so there is no aggregate to import or dispose of where the ground and loads allow mats without a stone base. Some routes need a base under the mats, a heavier class, or both.
We do not publish carbon savings figures. We show the comparison for your route, with the assumptions written down, so the scheme can make the call.
Send the layout, the constraint plans and any permit conditions with your enquiry. We plan the matting to them and say where a route needs more than matting.
Utility routes often have to cross live services. Matting can be part of a protected crossing, but the crossing point, the protection and any conditions are set by whoever owns the service. Ask the owner before the layout is fixed.


The better the constraint information, the closer the first proposal will be to the route the scheme can actually use.
Site address, postcode and the route or working area marked on a drawing.
Extracts from the environmental, soil and tree plans that cover temporary access.
Trees, watercourses, protected sites, invasive plants and buried services.
Plant and vehicles, traffic frequency, and the install and removal dates.
Any permit, assent or landowner conditions already issued for the work.
Photographs of the ground now, and how the land must be handed back.
The objective is a route that fits the scheme's commitments, not a generic mat count. Where a section needs more than matting, we say so.
Sources checked 4 October 2026, with the Natural England and Environment Agency guidance rechecked 5 October 2026. This guide supports access planning and procurement discussion. It is not legal, permit or arboricultural advice, and it is not a temporary works design.
For utility and infrastructure access, see utility and infrastructure access. For a defined vehicle route or haul road, see temporary roadway hire. For heavy plant, see the TM200 MegaDeck HD+. For wet winter ground, read clay ground in winter. TrackMatz reviews the project details before a proposal is issued.