HomeCase Studies200m event roadway
Completed event-access case studyInstallation and uplift recorded

200m Event Roadway. From installation to uplift.

A UK outdoor event needed a clearly managed temporary vehicle route across grass. TrackMatz supplied, installed and uplifted 167 connected TM50 mats to create a 200m × 2.4m roadway.

Completed 200 metre temporary event roadway formed from TM50 mats across grassThe completed route after installation.
200mTemporary roadway
2.4mInstalled width
167TM50 mats
334Joiners accounted for
The requirement

A defined vehicle route across an open grass site.

The project required a clearly marked route for controlled event traffic across the field. The 200m alignment connected the working areas while keeping vehicles on one planned running surface.

TM50 mats were joined into a continuous 2.4m-wide route. A temporary 5 mph sign made the operating limit visible at the approach.

Recorded sequence

Installed, used and uplifted.

TM50 temporary roadway immediately before uplift
01 · Before upliftThe temporary roadway remained defined across the grass at the end of the hire.
TrackMatz team uplifting TM50 mats from the event route
02 · UpliftThe route was removed in sequence and the supplied components were recovered.
Grass route photographed immediately after the TM50 mats were uplifted
03 · Ground recordThe route was photographed immediately after the final mats were lifted.
Post-uplift view of the temporary roadway route across grassPhotographed immediately after uplift.
Recorded outcome

The complete route was recovered and accounted for.

After the event, TrackMatz uplifted the full 200m temporary roadway. All 167 TM50 mats and 334 joiners were returned and accounted for.

Photographs taken immediately after uplift show a broadly level route with no deep rutting visible across the photographed area. The visible route marking is described as photographed, rather than presented as a wider condition guarantee.

Evidence boundary: this result belongs to the recorded site, weather, traffic and operating conditions. It is not automatic approval for another route or event.
✓ Full 200m route uplifted✓ Mats and joiners counted✓ Ground condition photographed✓ Project record completed
Planning an event route?

Start with the ground, traffic, route and programme.

Share the route length, ground photographs, expected vehicles and dates so TrackMatz can review the product class, quantity and installation approach.

Make the first review useful.

Include the site postcode, a marked route, expected vehicle types, traffic frequency and event dates.